== P1.3 Install the instrument in the cleanroom with its electronics cabinet == • **Phase** : 1 • **Status** : Draft • **Category** : Installation, integration, verification (C1) • **Recurrence** : once • **Duration** : 4 hour(s) **Description** • Install and integrate the different SHARK-NIR opto-mechanical components onto the mechanical structure. Install the electronics cabinets. Move the unit to the cleanroom. **Prerequisites** • All the necessary tools and safety features to do the installation, integration, and moving to the cleanroom. The mechanical structure to hold SHARK-NIR at the cleanroom should be assembled and ready to be used (with the possibility to move to cleanroom). **Procedure** • Carefully assemble and integrate the various opto-mechanical components. • Install them one by one onto the mechanical structure (either at mountain bay or at the clean room). • Install the electronics cabinet. **Success criteria** • The SHARK-NIR is primarily assembled on to the mechanical structure. • Electronics cabinets are installed. **Notes** **LBTO support** • Crane operator to lift and move stuff. • 1-2 crew to support installation on the mechanical structure. **Associated SHARK-NIR personnel** • JF, LM, MdP, **Date performed and by whom**