docs/CommissioningPlan/P1.3
v44 v45 51 51 ** Result** 52 52 - Newport optical bench, a table, monitor, and keyboard were brought by the LBT team to populate the clean tent as per SHARK-NIR requests. UPS will arrive soon. 53 -SHARK-NIR on its handling and Zarges boxes 10,11,12,13,16 were brought into the clean room. 54 -Electronics were mounted on the rack. 55 -SHARK-NIR and rack were rolled into the clean room, ready for cabling. 53 - SHARK-NIR on its handling and Zarges boxes 10,11,12,13,16 were brought into the clean room. 54 - Electronics were mounted on the rack. 55 - SHARK-NIR and rack were rolled into the clean room, ready for cabling. 56 56 57 57 58