    5151** Result**
    5252- Newport optical bench, a table, monitor, and keyboard were brought by the LBT team to populate the clean tent as per SHARK-NIR requests. UPS will arrive soon.
    53 -SHARK-NIR on its handling and Zarges boxes 10,11,12,13,16 were brought into the clean room.
    54 -Electronics were mounted on the rack.
    55 -SHARK-NIR and rack were rolled into the clean room, ready for cabling.
     53- SHARK-NIR on its handling and Zarges boxes 10,11,12,13,16 were brought into the clean room.
     54- Electronics were mounted on the rack.
     55- SHARK-NIR and rack were rolled into the clean room, ready for cabling.