docs/CommissioningPlan/P1.3
v42 v43 49 49 [[Image(SHAR-NIR_remove_fan_over_DM_electronics.jpg,88%)]] 50 50 51 ** Result** 52 - Newport optical bench, a table, monitor, and keyboard were brought by the LBT team to populate the clean tent as per SHARK-NIR requests. UPS will arrive soon. 53 -SHARK-NIR on its handling and Zarges boxes #10,11,12,13,16 were brought into the clean room. 54 -Electronics were mounted on the rack. 55 -SHARK-NIR and rack were rolled into the clean room, ready for cabling. 56 57 51 58 **Date performed and by whom** 59 - Maria, Luca, Davide, Marco, Simone, Jacopo 60 - LBTO staff 52 61