    4949[[Image(SHAR-NIR_remove_fan_over_DM_electronics.jpg,88%)]]
    5050
     51** Result**
     52- Newport optical bench, a table, monitor, and keyboard were brought by the LBT team to populate the clean tent as per SHARK-NIR requests. UPS will arrive soon.
     53-SHARK-NIR on its handling and Zarges boxes #10,11,12,13,16 were brought into the clean room.
     54-Electronics were mounted on the rack.
     55-SHARK-NIR and rack were rolled into the clean room, ready for cabling.
     56
     57
    5158**Date performed and by whom**
     59- Maria, Luca, Davide, Marco, Simone, Jacopo
     60- LBTO staff