Changes between Version 22 and Version 23 of docs/CommissioningPlan/P1.3


Ignore:
Timestamp:
02/14/22 14:47:26 (3 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P1.3

    v22 v23  
    77
    88**Description**
    9 - Install and integrate the different SHARK-NIR opto-mechanical components onto the mechanical structure. Install the electronics cabinets, and move the unit to the cleanroom.
     9- Install and integrate the different SHARK-NIR opto-mechanical components onto the mechanical structure. Install the electronics into a temporary rack, and move the unit to the cleanroom.
    1010
    1111**Prerequisites**
     
    1414**Procedure**
    1515- Carefully integrate the cryostat unit with the derotator-optical bench unit.
    16 - Before installing the motor electronics rack in the cleanroom, take it to the LBT Platform cabinet (its final destination) shared with iLocater for sanity checks.
     16- Before installing the electronics into a temporary rack in the cleanroom, take it to the LBT Platform cabinet at Level-6 (its final destination) shared with iLocater for sanity checks.
    1717- Set up the electronics racks in the cleanroom.
    1818
     
    2929**LBTO support**
    3030- Crane operator to lift and move stuff (mountain bay and/or cleanroom).
     31- Forklift to move boxes.
    3132- 1-2 crew to support installation procedure (mountain bay and/or cleanroom).
    3233- Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed.
    3334- Optical bench and access to the clean tent.
     35- If LBTO has an electronics rack available to mount the SHARK-NIR electronics for the duration from unboxing to installation at the telescope platform, SHARK-NIR can avoid shipping what we have from Padova. What we have in Padova has the following dimensions 58cm x 71cm x 185cm approximately, but a shorter one would still be acceptable for us. Below is the photo of our rack in Padova.
     36
     37[[Image(Shark-nir_ElectronicsRack_Padova.JPEG,50%)]]
    3438
    3539**Date performed and by whom**