wiki:docs/CommissioningPlan/P1.2

Version 5 (modified by mbergomi, 4 years ago) (diff)

--

P1.2 Opening boxes and their visual inspection

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, Verification, and Installation (C1)
  • Recurrence : once
  • Duration : half a day

Description

  • Unpack the containers/boxes carefully and visually inspect the components inside

Prerequisites

  • All the necessary tools and safety features to do the unpacking and moving.

Procedure

  • Carefully unpack the containers/boxes containing the SHARK-NIR opto-mechanical components.
  • Visually inspect if all the contents are safe and secure.
  • Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).

Success criteria

  • No damage to any container or boxes.

Notes

LBTO support

  • Crane operator to lift and move stuff.
  • 1-2 crew to support unpacking and moving.

Associated SHARK-NIR personnel

Date performed and by whom

Comments

MB:I would add to move all needed box contents in the clean room