P1.2 Opening of boxes in LBT Hall, inspection of the contents and installation of units on their handlings

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, and Verification (C1)
  • Recurrence : once
  • Duration : 1 day

Description

  • Unpack the containers/boxes carefully and visually inspect the components inside.

Prerequisites

  • All the necessary tools and safety features to unpack and move.

Procedure

  • Carefully unpack the containers/boxes containing the SHARK-NIR opto-mechanical components.
  • Visually inspect if all the contents are safe and secure.
  • Inspect if the tilt and shock sensors are activated or not.
  • Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).
  • Set up the handlings for the cryostat and the optical bench. Install the corresponding onto the handling and move to the cleanroom.

Templates

Success criteria

  • No damage to any container or boxes.
  • No shock sensors activated.

Notes

  • See AD10 for more details.

LBTO support

  • Crane operator (mountain bay) to lift and move stuff.
  • 1-2 crew to support unpacking and to move.

Date performed and by whom