    1212•       Carefully unpack the containers/boxes containing the SHARK-NIR opto-mechanical components.
    1313•       Visually inspect if all the contents are safe and secure.
     14* Inspect if the tilt and shock sensors are activated or not.
    1415•       Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).
    1516* Set up the handlings for the cyostat and the optical bench. install the corresponding onto the handling and move to the cleanroom.
     
    1718**Success criteria**
    1819•       No damage to any container or boxes.
     20* No shock sensors activated.
    1921**Notes**
    2022
     
    2830**Comments**
    2931
    30 LM: Same here about the tilt and shock sensor, as I would place some of them also inside the boxes.
     32LM: Same here about the tilt and shock sensor, as I would place some of them also inside the boxes. [DONE]