== P1.11 Instrument re-alignment == - **Phase** : 1 - **Status** : Draft - **Category** : Unpack, Assemble, and Verification (C1) - **Recurrence** : once - **Duration** : 1-6 days **Description** - In case, the internal alignment verification (P1.10) points in the direction of misalignments, the SHARK-NIR needs to be re-aligned. **Prerequisites** - SHARK-NIR is connected to the LBT network. - Electronics cabinets on. - The cryostat should be running and cooled down. - Access to the clean tent. **Procedure** - TBW **Templates** **Success criteria** - Perform P1.10 again after the re-alignment, and make sure the optical quality is within specifications. **Notes** - The actual number of days for this activity cannot be specified at this point. It could be between 1 day to a maximum of 6 days (TBC). **LBTO support** - Liquid Nitrogen refill is required in the cleanroom. - We will need lights ON and OFF during the re-alignment of the instrument inside the cleanroom. - 4D interferometer (TBC). - Access to the clean tent. **Date performed and by whom**