wiki:docs/CommissioningPlan/P1.10

Version 15 (modified by elcarolo, 3 years ago) (diff)

--

P1.10 NCPA routine verification

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, and Verification (C1)
  • Recurrence : once at commissioning
  • Duration : 1 day

Description

  • Check the working of the internal NCPA routine (phase diversity + ALPAO-DM)

Prerequisites

  • SCICAM cooled down.

Procedure

  • Run the Phase-diversity routine using the images taken with the SHARK-NIR internal calibration sources to measure the NCPA within (excluding the deployable arm).

Templates

  • SHARKNIR_di_cal_NCPA (not released)

Success criteria

  • Internal NCPA routine works fine and the PSF shows improvement in its quality.

Notes

LBTO support

  • Liquid Nitrogen refill is required in the cleanroom.

Date performed and by whom