Version 13 (modified by kradhakrishnan, 3 years ago) (diff) |
---|
P1.10 NCPA routine verification
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, and Verification (C1)
- Recurrence : once at commissioning
- Duration : 0.5 day
Description
- Check the working of the internal NCPA routine (phase diversity + ALPAO-DM)
Prerequisites
- SCICAM cooled down.
Procedure
- Run the Phase-diversity routine using the images taken with the SHARK-NIR internal calibration sources to measure the NCPA within (excluding the deployable arm).
Templates
Success criteria
- Internal NCPA routine works fine and the PSF shows improvement in its quality.
Notes
LBTO support
- Liquid Nitrogen refill is required in the cleanroom.
Date performed and by whom