SHARK-NIR Commissioning Activities List

This is an evolving page and the lists and activities will evolve in time as we gain more and more experience.

Although it is mentioned as the commissioning activities list, it lists all the activities of SHARK-NIR from its unpacking at LBT till the Science Verification, with the exception of the instrument installation at the LBT Bent Gregogian Central focal station.

The commissioning is broadly divided into 3 Phases:

Phase 1: We start from inspecting the boxes at LBT mountain bay, unpacking and installing the instrument at the mountain lab for alignment verification and functionality checks. All of these are daytime activities.

Phase 2: The activities after the installation of SHARK-NIR at the SX central bent Gregorian focus of LBT to the acquirement of the first nighttime telescope collimation model of the instrument form the Phase 2. Most of the activities are daytime. The only nighttime activity is to check the pointing, acquisition sequence and getting the first nighttime telescope collimation model for SHARK-NIR.

Phase 3: Phase 3 of the commissioning starts from sending preset to the telescope to testing individual SHARK-NIR observation modes for performance to the total SHARK-NIR performance. All the activities are nighttime. By the end of this phase, SHARK-NIR is ready for Science Verification.

Note that the corresponding evolving doc in SHARK-NIR Dropbox folder is SHARK-NIR Commissioning Plan with document number SHARK-NIR-INAFP-COM-001.

Applicable Documents

No. Title Number & Issue
AD1 SHARK-NIR Schedule SHARK-NIR-INAFP-Schedule-FDR Issue 0.3
AD2 SHARK-NIR SW ICD SHARK-NIR-INAFP-SW-ICD-FDR Issue 0.4
AD3 SHARK-NIR Installation Plan SHARK-NIR-INAFP-IP-001 Issue 0.1
AD4 SHARK-NIR Calibrations SHARK-NIR-INAFP-MAN-004

Category

The table below lists the categories of commissioning activities.

Category NameCategory Number
Installation, integration, verification C1
Daytime testing (functionality and operability)C2
Daytime calibrationC3
Nighttime testing (functionality and operability)C4
Nighttime calibrationC5
Nighttime testing for performanceC6

Phase 1

NumberActivity NameDay / NightDuration (mins)Maximum Duration (mins)CategoryLBTO SupportSHARK-NIR Location
P1.1Inspection of the boxesDay4040C1-mountain bay
P1.2Opening boxes and their visual inspectionDay6060C1crane operator to lift and move containers/boxes, 1-2 crew to support unpacking and movingmountain bay
P1.3Install the instrument in the cleanroom with its electronics cabinetDay240240C1crane operator to lift and move containers/boxes, 1-2 crew to support installation on the mechanical structuremountain bay + clean room
P1.4Cable in the instrument, power on, and connect to LBT networkDay120120C1support to connect to LBT network? Any electronics support?clean room
P1.5Start all the services and initialize all the motorsDay2020C1-clean room
P1.6Cool down the cryostatDay480480C1Liquid N2 fillclean room
P1.7Verification of the operability of the motors and light sourcesDay6060C1-clean room
P1.8Verification of the internal alignment of the instrumentDay120120C1-clean room
P1.9Science detector calibrationsDay6060C1-clean room

Phase 2

NumberActivity NameDay / NightDuration (mins)Maximum Duration (mins)CategoryLBTO SupportSHARK-NIR Location
P2.1Activating the instrument and testing instrument states & transitionsDay60 60C2Verify the working of emergency buttonLBT platform
P2.2Instrument operability and performanceDay180180C2-LBT platform
P2.3TCS communication testDay6060C2Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry and details for the fitswriterLBT platform
P2.4Align SHARK-NIR to the telescopeDay120120C2Mounting RR on the SX side. Support from LBTI?LBT platform
P2.5Synergy with LBTI AO system testDay120120C2Mounting RR on the SX side. Support from LBTI for AO runningLBT platform
P2.6Measurement of NCPADay180180C3Mounting RR on the SX side, Support from LBTI for AO runningLBT platform
P2.7Looking for filter defects/effects/featuresDay6060C2Support from LBTI for AO runningLBT platform
P2.8Flexure testsDay180180C2Support from LBTI for AO runningLBT platform
P2.9Nighttime acquisition and setting telescope collimation for nightNight180180C4Support from LBTI for AO runningLBT platform

Phase 3

NumberActivity NameDay / NightDuration (mins)Maximum Duration (mins)CategoryLBTO SupportSHARK-NIR Location
P3.1Telescope control – sending presetNight1010C4LBTI(AO), presence of John Hill while collimating, Steve Allensen as TOLBT platform
P3.2Telescope control – checking focus for different wavelengthsNight1030C4-LBT platform
P3.3Telescope control – telescope mode and offsetNight3030C4LBTI(AO)LBT platform
P3.4Telescope control – focal plane geometry estimationNight1060C4LBTI(AO)LBT platform
P3.5Check the acquisition procedureNight6060C4LBTI(AO)LBT platform
P3.6Orient the coronagraphsNight2040C4LBTI(AO)LBT platform
P3.7Estimate the instrument throughputNight1050C4LBTI(AO)LBT platform
P3.8Estimate the limiting magnitude for every filterNight1050C4LBTI(AO)LBT platform
P3.9Estimate sky background for broadband filtersNight1050C4LBTI(AO)LBT platform
P3.10Verify the ADC rotation on skyNight2040C4LBTI(AO)LBT platform
P3.11Ghost positions on the SCICAMNight1050C4LBTI(AO)LBT platform
P3.12Checking field-stabilized mode/bearing rotation serviceNight2040C4LBTI(AO)LBT platform
P3.13Center the slitNight4040C4LBTI(AO)LBT platform
P3.14Astrometry plate scale and orientationNight-30C5LBTI(AO)LBT platform
P3.15Flux calibration (off-centered target observation)Night-20C5LBTI(AO)LBT platform
P3.16Instrumental throughput and absolute flux calibrationNight2040C5LBTI(AO)LBT platform
P3.17Atmospheric calibration and absolute flux calibrationNight-20C5LBTI(AO)LBT platform
P3.18Large spatial scale instrument and telescope flat fieldNight-60C5LBTI(AO)LBT platform
P3.19Sky backgroundNight-10C5LBTI(AO)LBT platform
P3.20Instrumental background for scienceDay-20C3-LBT platform
P3.21Star centerNight-20C5LBTI(AO)LBT platform
P3.22Instrument flat field, detector linearity and bad pixelsDay-20C3-LBT platform
P3.23Wavelength calibrationDay-10C3-LBT platform
P3.24Thermal backgroundDay-60C3-LBT platform
P3.25Detector gainDay-20C3-LBT platform
P3.26Detector persistenceDay-20C3-LBT platform
P3.27Spectral resolutionDay-10C3-LBT platform
P3.28Ghost calibrationDay2060C3-LBT platform
P3.29Distortion mapNight-10C5LBTI(AO)LBT platform
P3.30Filter wheels reproducibility monitoringDay-20C3-LBT platform
P3.31Pupil alignmentNight-5C5LBTI(AO)LBT platform
P3.32PSF AlignmentNight-5C5LBTI(AO)LBT platform