Changes between Version 9 and Version 10 of docs/CommissioningActivityList


Ignore:
Timestamp:
03/04/20 17:17:41 (5 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningActivityList

    v9 v10  
    1212 **Phase 3**: Phase 3 of the commissioning starts from sending preset to the telescope to testing individual SHARK-NIR observation modes for performance to the total SHARK-NIR performance. All the activities are nighttime. By the end of this phase, SHARK-NIR is ready for Science Verification.
    1313
    14 Note that the corresponding evolving doc in SHARK-NIR Dropbox folder is **SHARK-NIR Commissioning Plan ** with document number **SHARK-NIR-INAFP-COM-001**.
     14Note that the corresponding evolving doc in SHARK-NIR Dropbox folder is **SHARK-NIR-INAFP-COM-001_CommissioningPlan.docx**. There is also an excel file listing the activities titled **SHARK-NIR-INAFP-COM-002_CommissioningActivityList.xlsx**.
    1515
    1616== Applicable Documents ==