66 | | ||P1.1||Inspection of the boxes||Day||40||40||C1||-|| |
67 | | ||P1.2||Opening boxes and their visual inspection||Day||60||60||C1||crane operator to lift and move containers/boxes, 1-2 crew to support unpacking and moving|| |
68 | | ||P1.3||Install the instrument in the cleanroom with its electronics cabinet||Day||240||240||C1||crane operator to lift and move containers/boxes, 1-2 crew to support installation on the mechanical structure|| |
69 | | ||P1.4||Cable in the instrument, power on, and connect to LBT network||Day||120||120||C1||support to connect to LBT network? Any electronics support?|| |
70 | | ||P1.5||Start all the services and initialize all the motors||Day||20||20||C1||-|| |
71 | | ||P1.6||Cool down the cryostat||Day||480||480||C1||Liquid N2 fill|| |
72 | | ||P1.7||Verification of the operability of the motors and light sources||Day||60||60||C1||-|| |
73 | | ||P1.8||Verification of the internal alignment of the instrument||Day||120||120||C1||-|| |
74 | | ||P1.9||Science detector calibrations||Day||60||60||C1||-|| |
| 66 | ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the boxes]||Day||40||40||C1||-|| |
| 67 | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes and their visual inspection]||Day||60||60||C1||crane operator to lift and move containers/boxes, 1-2 crew to support unpacking and moving|| |
| 68 | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Install the instrument in the cleanroom with its electronics cabinet]||Day||240||240||C1||crane operator to lift and move containers/boxes, 1-2 crew to support installation on the mechanical structure|| |
| 69 | ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, and connect to LBT network]||Day||120||120||C1||support to connect to LBT network? Any electronics support?|| |
| 70 | ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 Start all the services and initialize all the motors]||Day||20||20||C1||-|| |
| 71 | ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cool down the cryostat]||Day||480||480||C1||Liquid N2 fill|| |
| 72 | ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Verification of the operability of the motors and light sources]||Day||60||60||C1||-|| |
| 73 | ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Verification of the internal alignment of the instrument]||Day||120||120||C1||-|| |
| 74 | ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Science detector calibrations]||Day||60||60||C1||-|| |
79 | | ||P2.1||Activating the instrument and testing instrument states & transitions||Day||60 ||60||C2||Verify the working of emergency button|| |
80 | | ||P2.2||Instrument operability and performance||Day||180||180||C2||-|| |
81 | | ||P2.3||TCS communication test||Day||60||60||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry and details for the fitswriter|| |
82 | | ||P2.4||Align SHARK-NIR to the telescope||Day||120||120||C2||Mounting RR on the SX side. Support from LBTI?|| |
83 | | ||P2.5||Synergy with LBTI AO system test||Day||120||120||C2||Mounting RR on the SX side. Support from LBTI for AO running|| |
84 | | ||P2.6||Measurement of NCPA||Day||180||180||C3||Mounting RR on the SX side, Support from LBTI for AO running|| |
85 | | ||P2.7||Looking for filter defects/effects/features||Day||60||60||C2||Support from LBTI for AO running|| |
86 | | ||P2.8||Flexure tests||Day||180||180||C2||Support from LBTI for AO running|| |
87 | | ||P2.9||Nighttime acquisition and setting telescope collimation for night||Night||180||180||C4||Support from LBTI for AO running|| |
| 79 | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||60 ||60||C2||Verify the working of emergency button|| |
| 80 | ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and performance]||Day||180||180||C2||-|| |
| 81 | ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||60||60||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry and details for the fitswriter|| |
| 82 | ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||120||120||C2||Mounting RR on the SX side. Support from LBTI?|| |
| 83 | ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Synergy with LBTI AO system test]||Day||120||120||C2||Mounting RR on the SX side. Support from LBTI for AO running|| |
| 84 | ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||180||180||C3||Mounting RR on the SX side, Support from LBTI for AO running|| |
| 85 | ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features]||Day||60||60||C2||Support from LBTI for AO running|| |
| 86 | ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Flexure tests]||Day||180||180||C2||Support from LBTI for AO running|| |
| 87 | ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Nighttime acquisition and setting telescope collimation for night]||Night||180||180||C4||Support from LBTI for AO running|| |
92 | | ||P3.1||Telescope control – sending preset||Night||10||10||C4||LBTI(AO), presence of John Hill while collimating, Steve Allensen as TO|| |
93 | | ||P3.2||Telescope control – checking focus for different wavelengths||Night||10||30||C4||-|| |
94 | | ||P3.3||Telescope control – telescope mode and offset||Night||30||30||C4||LBTI(AO)|| |
95 | | ||P3.4||Telescope control – focal plane geometry estimation||Night||10||60||C4||LBTI(AO)|| |
96 | | ||P3.5||Check the acquisition procedure||Night||60||60||C4||LBTI(AO)|| |
97 | | ||P3.6||Orient the coronagraphs||Night||20||40||C4||LBTI(AO)|| |
98 | | ||P3.7||Estimate the instrument throughput||Night||10||50||C4||LBTI(AO)|| |
99 | | ||P3.8||Estimate the limiting magnitude for every filter||Night||10||50||C4||LBTI(AO)|| |
100 | | ||P3.9||Estimate sky background for broadband filters||Night||10||50||C4||LBTI(AO)|| |
101 | | ||P3.10||Verify the ADC rotation on sky||Night||20||40||C4||LBTI(AO)|| |
102 | | ||P3.11||Ghost positions on the SCICAM||Night||10||50||C4||LBTI(AO)|| |
103 | | ||P3.12||Checking field-stabilized mode/bearing rotation service||Night||20||40||C4||LBTI(AO)|| |
104 | | ||P3.13||Center the slit||Night||40||40||C4||LBTI(AO)|| |
105 | | ||P3.14||Astrometry plate scale and orientation||Night||-||30||C5||LBTI(AO)|| |
106 | | ||P3.15||Flux calibration (off-centered target observation)||Night||-||20||C5||LBTI(AO)|| |
107 | | ||P3.16||Instrumental throughput and absolute flux calibration||Night||20||40||C5||LBTI(AO)|| |
108 | | ||P3.17||Atmospheric calibration and absolute flux calibration||Night||-||20||C5||LBTI(AO)|| |
109 | | ||P3.18||Large spatial scale instrument and telescope flat field||Night||-||60||C5||LBTI(AO)|| |
110 | | ||P3.19||Sky background||Night||-||10||C5||LBTI(AO)|| |
111 | | ||P3.20||Instrumental background for science||Day||-||20||C3||-|| |
112 | | ||P3.21||Star center||Night||-||20||C5||LBTI(AO)|| |
113 | | ||P3.22||Instrument flat field, detector linearity and bad pixels||Day||-||20||C3||-|| |
114 | | ||P3.23||Wavelength calibration||Day||-||10||C3||-|| |
115 | | ||P3.24||Thermal background||Day||-||60||C3||-|| |
116 | | ||P3.25||Detector gain||Day||-||20||C3||-|| |
117 | | ||P3.26||Detector persistence||Day||-||20||C3||-|| |
118 | | ||P3.27||Spectral resolution||Day||-||10||C3||-|| |
119 | | ||P3.28||Ghost calibration||Day||20||60||C3||-|| |
120 | | ||P3.29||Distortion map||Night||-||10||C5||LBTI(AO)|| |
121 | | ||P3.30||Filter wheels reproducibility monitoring||Day||-||20||C3||-|| |
122 | | ||P3.31||Pupil alignment||Night||-||5||C4||LBTI(AO)|| |
123 | | ||P3.32||PSF Alignment||Night||-||5||C4||LBTI(AO)|| |
| 92 | ||P3.1||[wiki:/docs/CommissioningPlan/P3.1 Telescope control – sending preset]||Night||10||10||C4||LBTI(AO), presence of John Hill while collimating, Steve Allensen as TO|| |
| 93 | ||P3.2||[wiki:/docs/CommissioningPlan/P3.2 Telescope control – checking focus for different wavelengths]||Night||10||30||C4||-|| |
| 94 | ||P3.3||[wiki:/docs/CommissioningPlan/P3.3Telescope control – telescope mode and offset]||Night||30||30||C4||LBTI(AO)|| |
| 95 | ||P3.4||[wiki:/docs/CommissioningPlan/P3.4 Telescope control – focal plane geometry estimation]||Night||10||60||C4||LBTI(AO)|| |
| 96 | ||P3.5||[wiki:/docs/CommissioningPlan/P3.5 Check the acquisition procedure]||Night||60||60||C4||LBTI(AO)|| |
| 97 | ||P3.6||[wiki:/docs/CommissioningPlan/P3.6 Orient the coronagraphs]||Night||20||40||C4||LBTI(AO)|| |
| 98 | ||P3.7||[wiki:/docs/CommissioningPlan/P3.7 Estimate the instrument throughput]||Night||10||50||C4||LBTI(AO)|| |
| 99 | ||P3.8||[wiki:/docs/CommissioningPlan/P3.8 Estimate the limiting magnitude for every filter]||Night||10||50||C4||LBTI(AO)|| |
| 100 | ||P3.9||[wiki:/docs/CommissioningPlan/P3.9 Estimate sky background for broadband filters]||Night||10||50||C4||LBTI(AO)|| |
| 101 | ||P3.10||[wiki:/docs/CommissioningPlan/P3.10 Verify the ADC rotation on sky]||Night||20||40||C4||LBTI(AO)|| |
| 102 | ||P3.11||[wiki:/docs/CommissioningPlan/P3.11 Ghost positions on the SCICAM]||Night||10||50||C4||LBTI(AO)|| |
| 103 | ||P3.12||[wiki:/docs/CommissioningPlan/P3.12 Checking field-stabilized mode/bearing rotation service]||Night||20||40||C4||LBTI(AO)|| |
| 104 | ||P3.13||[wiki:/docs/CommissioningPlan/P3.13 Center the slit]||Night||40||40||C4||LBTI(AO)|| |
| 105 | ||P3.14||[wiki:/docs/CommissioningPlan/P3.14 Astrometry plate scale and orientation]||Night||-||30||C5||LBTI(AO)|| |
| 106 | ||P3.15||[wiki:/docs/CommissioningPlan/P3.15 Flux calibration (off-centered target observation)]||Night||-||20||C5||LBTI(AO)|| |
| 107 | ||P3.16||[wiki:/docs/CommissioningPlan/P3.16 Instrumental throughput and absolute flux calibration]||Night||20||40||C5||LBTI(AO)|| |
| 108 | ||P3.17||[wiki:/docs/CommissioningPlan/P3.17 Atmospheric calibration and absolute flux calibration]||Night||-||20||C5||LBTI(AO)|| |
| 109 | ||P3.18||[wiki:/docs/CommissioningPlan/P3.18 Large spatial scale instrument and telescope flat field]||Night||-||60||C5||LBTI(AO)|| |
| 110 | ||P3.19||[wiki:/docs/CommissioningPlan/P3.19 Sky background]||Night||-||10||C5||LBTI(AO)|| |
| 111 | ||P3.20||[wiki:/docs/CommissioningPlan/P3.20 Instrumental background for science]||Day||-||20||C3||-|| |
| 112 | ||P3.21||[wiki:/docs/CommissioningPlan/P3.21 Star center]||Night||-||20||C5||LBTI(AO)|| |
| 113 | ||P3.22||[wiki:/docs/CommissioningPlan/P3.22 Instrument flat field, detector linearity and bad pixels]||Day||-||20||C3||-|| |
| 114 | ||P3.23||[wiki:/docs/CommissioningPlan/P3.23 Wavelength calibration]||Day||-||10||C3||-|| |
| 115 | ||P3.24||[wiki:/docs/CommissioningPlan/P3.24 Thermal background]||Day||-||60||C3||-|| |
| 116 | ||P3.25||[wiki:/docs/CommissioningPlan/P3.25 Detector gain]||Day||-||20||C3||-|| |
| 117 | ||P3.26||[wiki:/docs/CommissioningPlan/P3.26 Detector persistence]||Day||-||20||C3||-|| |
| 118 | ||P3.27||[wiki:/docs/CommissioningPlan/P3.27 Spectral resolution]||Day||-||10||C3||-|| |
| 119 | ||P3.28||[wiki:/docs/CommissioningPlan/P3.28 Ghost calibration]||Day||20||60||C3||-|| |
| 120 | ||P3.29||[wiki:/docs/CommissioningPlan/P3.29 Distortion map]||Night||-||10||C5||LBTI(AO)|| |
| 121 | ||P3.30||[wiki:/docs/CommissioningPlan/P3.30 Filter wheels reproducibility monitoring]||Day||-||20||C3||-|| |
| 122 | ||P3.31||[wiki:/docs/CommissioningPlan/P3.31 Pupil alignment]||Night||-||5||C4||LBTI(AO)|| |
| 123 | ||P3.32||[wiki:/docs/CommissioningPlan/P3.32 PSF Alignment]||Night||-||5||C4||LBTI(AO)|| |